3. You are overseeing a data center project for one of your clients. The team members have finished creating the Work Breakdown Structure (WBS) and Work Breakdown Structure Dictionary. The team members also submitted their activity duration estimates to you. What should you focus on NEXT
A. Sequence the activities using the precedence diagramming method.correct
B. Create the activity list.
C. Determine high-level project assumptions and constraints.
D. Develop the project schedule.
What is the correct answer..