Hi Rahul/Shri,
I need to know if this explantion is correct.1. Verified deliverables are inputs in which of the following scope management processes?
A. Define Scope
B. Create WBS
C. Validate Scopecorrect
D. Control Scope
Verified deliverables are the deliverables that have been completed as per the documented scope and checked for defects by the project team members in the Control Quality process. These deliverables are inputs in the Validate Scope process and are given to the customers and stakeholders for their acceptance.
2. A project manager is in the Collect Requirements process of collecting and documenting quantifiable needs and expectations of the sponsor, customer, and other stakeholders. Which of the following is NOT true regarding this process?
A. It describes project deliverables and the work required to create them in detail as well as deliverables description, product acceptance criteria,requirements assumptions and constraints, and exclusions from requirements.correct
B. Requirements Documentation and Requirements Traceability Matrix are thekey outputs in this process.wrong
C. Various Data Gathering Techniques and Decision Making techniques are used as tools & techniques in this process.
D. The Scope Management Plan and Requirements Management Plan are inputs in this process.Explanation:
The Project Scope Statement, not the Requirements Documentation, describes project deliverables and the work required to create them in detail as well as the deliverables description, product acceptance criteria, requirements assumptions and constraints, and exclusions from requirements.
-
-